Back to projects

Hanlon Creek Business Park Multi-Use Path

Guelph, Ontario

completeActive TransportationCVRIS
Federal contribution
$558,610
Federal share80%

of $698.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
2022
Built

Approved 5 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 18, 2021(actual)
Construction end
Sep 29, 2022(actual)

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60225 in the federal list. How to read these figures.