Schoolyard repairs
Federal contribution
$46,400
Federal share80%
of $58.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 1, 2023(actual)
- Construction end
- Jun 25, 2024(actual)
Against the original forecast
- Construction end6 months earlyforecast Dec 31, 2024
Also in La Tuque
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60243 in the federal list. How to read these figures.