Back to projects

Renovation of outdoor facilities

Shawinigan, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$349,600
Federal share80%

of $437.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 2, 2022(actual)
Construction end
Aug 23, 2022(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Jun 30, 2022
  • Construction end2 months earlyforecast Oct 30, 2022

Also in Shawinigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60246 in the federal list. How to read these figures.