Repair of interior finishes
Federal contribution
$644,000
Federal share80%
of $805.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Apr 10, 2023(actual)
- Construction end
- Apr 27, 2024(actual)
Against the original forecast
- Construction start2 months lateforecast Feb 6, 2023
- Construction end8 months earlyforecast Dec 31, 2024
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60251 in the federal list. How to read these figures.