Parking lot repairs and work on classrooms
Federal contribution
$513,832
Federal share80%
of $642.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 21, 2021(actual)
- Construction end
- Aug 27, 2021(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2021
- Construction end5 weeks earlyforecast Oct 1, 2021
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60257 in the federal list. How to read these figures.