Replacement of interior finish
Federal contribution
$525,063
Federal share80%
of $656.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de la Pointe-de-l'Île
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Mar 15, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end3 months lateforecast Dec 17, 2021
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60261 in the federal list. How to read these figures.