Replacement of the interior finish (phase 1)
Federal contribution
$870,086
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de la Pointe-de-l'Île
- Construction start
- May 25, 2021(actual)
- Construction end
- Dec 15, 2022(actual)
Against the original forecast
- Construction end12 months lateforecast Dec 17, 2021
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60264 in the federal list. How to read these figures.