Replacement of masonry
Federal contribution
$446,400
Federal share80%
of $558.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de la Pointe-de-l'Île
- Construction start
- Jun 29, 2021(actual)
- Construction end
- Dec 15, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end7 weeks lateforecast Oct 30, 2022