Replacement of natural gas boilers
Federal contribution
$229,436
Federal share57%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- May 3, 2021(actual)
- Construction end
- Oct 7, 2021(actual)
Against the original forecast
- Construction end5 weeks lateforecast Sep 1, 2021