Replacing an air conditioning unit
Federal contribution
$490,708
Federal share80%
of $613.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de la Pointe-de-l'Île
- Construction start
- Apr 5, 2021(actual)
- Construction end
- Dec 15, 2022(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Jun 1, 2021
- Construction end7 weeks lateforecast Oct 30, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60287 in the federal list. How to read these figures.