Upgrading of the backflow preventer, the meter, the water cut-off system and the domestic water inlet valve and the drinking water distribution network

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$264,880
Federal share80%

of $331.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 2, 2022(actual)
Construction end
Sep 20, 2023(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 19, 2022
  • Construction end4 months lateforecast Jun 2, 2023