Boiler room refurbishment & interior renovations
Federal contribution
$653,771
Federal share80%
of $817.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Jan 19, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end23 months earlyforecast Dec 31, 2024
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60329 in the federal list. How to read these figures.