Boiler room refurbishment & interior renovations

Shawinigan, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$653,771
Federal share80%

of $817.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
Jan 19, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end23 months earlyforecast Dec 31, 2024