Repair of exterior cladding and paving
Federal contribution
$483,474
Federal share80%
of $604.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- May 2, 2022(actual)
- Construction end
- Dec 5, 2022(actual)
Against the original forecast
- Construction start11 months lateforecast Jun 1, 2021
- Construction end5 weeks lateforecast Oct 30, 2022
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60339 in the federal list. How to read these figures.