Back to projects

Repair of the heating system

Shawinigan, Quebec

completeVentilationCVRIS
Federal contribution
$136,000
Federal share80%

of $170.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 29, 2021(actual)
Construction end
Dec 1, 2022(actual)

Against the original forecast

  • Construction start2 months earlyforecast Jun 1, 2021
  • Construction end5 weeks lateforecast Oct 30, 2022

Also in Shawinigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60340 in the federal list. How to read these figures.