Replacement ventilation and repair of interior finishes
Federal contribution
$472,444
Federal share80%
of $590.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
2022
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Jul 12, 2022(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end3 months earlyforecast Oct 1, 2022
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60359 in the federal list. How to read these figures.