Renovation of sanitary blocks

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$437,525
Federal share80%

of $546.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 3, 2021(actual)
Construction end
Mar 7, 2022(actual)

Against the original forecast

  • Construction end6 weeks lateforecast Jan 24, 2022