Renovation of Sanitary Blocks and Change Rooms - Phase 1
Federal contribution
$1.8M
$1,812,880
Federal share80%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 6, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de Montréal (CSSDM)
- Construction start
- Jun 27, 2022(actual)
- Construction end
- Jul 6, 2023(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 9, 2022
- Construction end5 weeks lateforecast Jun 2, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60364 in the federal list. How to read these figures.