Castlegar - Library and Airport Roof Replacements

Castlegar, British Columbia

completeVentilationCVRIS
Federal contribution
$236,633
Federal share80%

of $295.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
202220232024
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Castlegar
Construction start
Aug 20, 2022(actual)
Construction end
Nov 30, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 12, 2022
  • Construction end2 weeks earlyforecast Dec 15, 2023

Also in Castlegar

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60396 in the federal list. How to read these figures.