Castlegar - Millennium Park Phase 3
Federal contribution
$654,400
Federal share40%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 11, 2022
20232024
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- City of Castlegar
- Construction start
- Aug 9, 2023(actual)
- Construction end
- Jun 12, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Mar 15, 2023
- Construction end3 weeks earlyforecast Jun 30, 2024
Also in Castlegar
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61490 in the federal list. How to read these figures.