Maple Hill Manor - Personal Protective Equipment Storage Garage
Federal contribution
$44,975
Federal share80%
of $56.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Maple Hill Manor
- Construction start
- Jun 14, 2021(actual)
- Construction end
- Oct 29, 2021(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2021
- Construction end2 months earlyforecast Dec 31, 2021
Also in New Waterford