Maple Hill Manor - Facility Upgrades
Federal contribution
$115,911
Federal share80%
of $144.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 27, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Maple Hill Manor
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Jan 22, 2022(actual)
Against the original forecast
- Construction end5 weeks lateforecast Dec 15, 2021
Also in New Waterford