Glen Haven Manor - Facility Upgrades
Federal contribution
$150,445
Federal share80%
of $188.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 7, 2024
202220232024
Built
Approved 2.9 years before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Glen Haven Manor
- Construction start
- Feb 14, 2022(actual)
- Construction end
- Feb 24, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Dec 1, 2021
- Construction end8 weeks lateforecast Dec 31, 2022
Also in New Glasgow
- New Glasgow Library and Pictou-Antigonish Regional Library (PARL) Headquarters Revitalization$3.9M
- Southend Sewer Separation (Phase II to IV)$1.5M
- New Glasgow Water Treatment Expansion$1.3M
- Water Transmission Line Replacement on East River East Side Road$1.2M
- Town of New Glasgow - Abercrombie Road Waterline Replacement$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60406 in the federal list. How to read these figures.