Summerland - Lakeshore Drive Improvements

Summerland, British Columbia

completeDisaster MitigationCVRIS
Federal contribution
$312,150
Federal share80%

of $390.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 15, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
District of Summerland
Construction start
Oct 24, 2022(actual)
Construction end
May 3, 2023(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Sep 30, 2022
  • Construction end7 months earlyforecast Nov 30, 2023

Also in Summerland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60440 in the federal list. How to read these figures.