Pelican Falls First Nations High School Road
Federal contribution
$678,005
Federal share80%
of $847.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Northern Nishnawbe Education Council
- Construction start
- Sep 25, 2023(actual)
- Construction end
- Oct 21, 2024(actual)
Against the original forecast
- Construction end7 weeks lateforecast Sep 1, 2024
Also in Sioux Lookout
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60468 in the federal list. How to read these figures.