Ginoogaming Classroom/Washroom Renovations

Ginoogaming First Nation, Ontario

completeVentilationCVRIS
Federal contribution
$160,294
Federal share80%

of $200.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Ginoogaming First Nation
Construction start
Oct 19, 2021(actual)
Construction end
May 13, 2022(actual)

Against the original forecast

  • Construction start11 months earlyforecast Oct 1, 2022
  • Construction end11 months earlyforecast Apr 28, 2023

Also in Ginoogaming First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60476 in the federal list. How to read these figures.