Capital purchasing of new and/or replacement of equipment for optimizing the water losses and high inflow/infiltration issues from the Ginoogaming First Nation

Ginoogaming First Nation, Ontario

completeWastewaterCWWF
Federal contribution
$20,132
Federal share48%

of $42.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Ginoogaming First Nation
Construction start
Jul 31, 2019(actual)
Construction end
Feb 28, 2020(actual)

Against the original forecast

  • Construction start12 months lateforecast Aug 1, 2018
  • Construction end4 months lateforecast Oct 31, 2019