Fort Severn First Nation - Portable Classroom Trailer
Fort Severn First Nation, Ontario
Federal contribution
$318,720
Federal share80%
of $398.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Fort Severn First Nation
- Construction start
- Oct 27, 2022(actual)
- Construction end
- Oct 7, 2024(actual)
Against the original forecast
- Construction start7 months earlyforecast Jun 1, 2023
- Construction end12 months lateforecast Sep 30, 2023
Also in Fort Severn First Nation
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60479 in the federal list. How to read these figures.