Fort Severn First Nation - Portable Classroom Trailer

Fort Severn First Nation, Ontario

completeEducation, Training and ChildcareCVRIS
Federal contribution
$318,720
Federal share80%

of $398.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 3, 2021
202220232024
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Fort Severn First Nation
Construction start
Oct 27, 2022(actual)
Construction end
Oct 7, 2024(actual)

Against the original forecast

  • Construction start7 months earlyforecast Jun 1, 2023
  • Construction end12 months lateforecast Sep 30, 2023

Also in Fort Severn First Nation

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60479 in the federal list. How to read these figures.