Back to projects

Improve Freeze protection on water main

Fort Severn First Nation, Ontario

completeDrinking WaterCWWF
Federal contribution
$13,387
Federal share50%

of $26.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 10, 2017
201820192020
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Fort Severn First Nation
Construction start
Jun 1, 2019(actual)
Construction end
Jun 30, 2020(actual)

Against the original forecast

  • Construction start11 months lateforecast Jul 1, 2018
  • Construction end3 months lateforecast Mar 31, 2020

Also in Fort Severn First Nation