Mowachaht Muchalaht First Nation - Community Centre / School Solar
Federal contribution
$396,850
Federal share100%
of $396.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Mowachaht Muchalaht First Nation
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Mar 1, 2023
- Construction end2 months earlyforecast Dec 31, 2023
Also in Gold River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60484 in the federal list. How to read these figures.