Beneficial Biosolids Reuse

Gold River, British Columbia

completeWastewaterCWWF
Federal contribution
$298,155
Federal share50%

of $596.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 17, 2017
2018201920202021
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Gold River
Construction start
Sep 1, 2017(actual)
Construction end
Jun 7, 2021(actual)

Against the original forecast

  • Construction start2.1 years earlyforecast Oct 21, 2019
  • Construction end22 months earlyforecast Mar 31, 2023