Gabriola Island Community Hall Association - Outdoor Community Gathering Space on Gabriola
Federal contribution
$203,324
Federal share80%
of $254.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Gabriola Island Community Hall Association
- Construction start
- May 15, 2023(actual)
- Construction end
- Aug 1, 2024(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 31, 2023
- Construction end5 months earlyforecast Dec 31, 2024
Also in Nanaimo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60520 in the federal list. How to read these figures.