Nisga'a Village of New Aiyansh - Gitlaxtaamiks Village Government - Skateen Drive Sidewalk Construction
Nisgaa Village of Gitlaxt'aamix (formerly New Aiyansh), British Columbia
Federal contribution
$742,333
Federal share100%
of $742.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 3, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Nisga'a Village of Gitlaxt'aamix (formerly New Aiyansh)
- Construction start
- Jul 24, 2023(actual)
- Construction end
- Sep 16, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
- Construction end3 months earlyforecast Dec 15, 2023
Also in Nisgaa Village of Gitlaxt'aamix (formerly New Aiyansh)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60550 in the federal list. How to read these figures.