Tait Avenue Sidewalk and Storm Water Management Upgrades for Gitlaxt'aamiks, BC
Nisgaa Village of Gitlaxt'aamix (formerly New Aiyansh), British Columbia
Federal contribution
$1.1M
$1,121,750
Federal share69%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 10, 2023
20232024
Built
Approved 8 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Nisga'a Village of Gitlaxt'aamix (formerly New Aiyansh)
- Construction start
- Jul 15, 2024(actual)
- Construction end
- Oct 26, 2024(actual)
Against the original forecast
- Construction start11 months lateforecast Jul 31, 2023
- Construction end12 months earlyforecast Oct 31, 2025
Also in Nisgaa Village of Gitlaxt'aamix (formerly New Aiyansh)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64341 in the federal list. How to read these figures.