Coliseum Electrical Upgrades
Federal contribution
$403,200
Federal share62%
of $654.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 2, 2021
202220232024
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Sep 13, 2021(actual)
- Construction end
- Aug 31, 2024(actual)
Against the original forecast
- Construction start4 months lateforecast May 4, 2021
- Construction end2 months earlyforecast Oct 31, 2024
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60587 in the federal list. How to read these figures.