Back to projects

Replace existing humidifiers in West Building

Toronto, Ontario

completeHealthcare InfrastructureCVRIS
Federal contribution
$21,000
Federal share80%

of $26.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 1, 2021(actual)
Construction end
Jun 30, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast May 3, 2021

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60617 in the federal list. How to read these figures.