City of Regina - Mobility Device Securement System
Federal contribution
$520,753
Federal share40%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
2022
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Regina
- Construction start
- Dec 1, 2021(actual)
- Construction end
- Jun 17, 2022(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2021
- Construction end6 months earlyforecast Dec 31, 2022
Also in Regina
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60634 in the federal list. How to read these figures.