Back to projects

Solar Microgrid for Bayside Travel Centre

Antigonish, Nova Scotia

completeGreen EnergyGIS
Federal contribution
$1.3M
$1,254,929
Federal share75%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 11, 2023
202320242025
Built

Approved 6 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 25, 2023(actual)
Construction end
Apr 4, 2025(actual)

Against the original forecast

  • Construction start3 weeks lateforecast May 1, 2023
  • Construction end9 months lateforecast Jun 30, 2024

Also in Antigonish