Back to projects

Regional Municipality of Wood Buffalo Real Martin Drive Trail Improvements

Wood Buffalo (Regional Municiaplity), Alberta

completeActive TransportationCVRIS
Federal contribution
$800,000
Federal share80%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2021
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jul 13, 2021(actual)
Construction end
Nov 26, 2021(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2021
  • Construction end5 weeks earlyforecast Dec 31, 2021

Also in Wood Buffalo (Regional Municiaplity)