Back to projects

Heating Boiler Plant (2) Retrofit to 'C' LTC home

Toronto, Ontario

completeVentilationCVRIS
Federal contribution
$217,832
Federal share80%

of $272.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 30, 2021(actual)
Construction end
Mar 31, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 30, 2021
  • Construction end18 months lateforecast Sep 30, 2021

Also in Toronto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60933 in the federal list. How to read these figures.