Rehabilitation of Riverside Park Sidewalk Pathway

Kapuskasing, Ontario

completeActive TransportationCVRIS
Federal contribution
$138,672
Federal share80%

of $173.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
20222023
Built
Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Kapuskasing
Construction start
Jul 26, 2021(actual)
Construction end
Dec 12, 2022(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Jun 1, 2021
  • Construction end2 months lateforecast Sep 30, 2022

Also in Kapuskasing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60975 in the federal list. How to read these figures.