The Société de transport de Laval garage expansion (Phase IV)
Federal contribution
$85.1M
$85,068,800
Federal share40%
of $212.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2021
today
202220232024202520262027
BuiltForecast
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Société de transport de Laval (STL)
- Construction start
- Dec 5, 2022(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in Laval
- Acquisition of 94 Electric Buses$59.5M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
- Deployment of comfortable and user-friendly cycling links and implementation of physical separations where possible, provided for in the master plan of the City of Laval's cycling network$10.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60981 in the federal list. How to read these figures.