Acquisition of 94 Electric Buses
Federal contribution
$59.5M
$59,460,466
Federal share40%
of $148.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 8, 2023
today
2024202520262027
BuiltForecast
Approved 6 weeks before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Société de transport de Laval (STL)
- Construction start
- Jul 16, 2025(actual)
- Construction end
- Dec 31, 2026(forecast)
Also in Laval
- The Société de transport de Laval garage expansion (Phase IV)$85.1M
- Updating drinking water treatment plants in Laval$46.8M
- Stabilization and revitalization work on the shore and Boulevard des Mille-Îles between Highway 25 and the eastern tip of Laval Island$25.3M
- Backflow controls of Monty sector - Laval$12.3M
- Deployment of comfortable and user-friendly cycling links and implementation of physical separations where possible, provided for in the master plan of the City of Laval's cycling network$10.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65700 in the federal list. How to read these figures.