PHI Contemporary
Federal contribution
$13.3M
$13,322,870
Federal share40%
of $33.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2022
today
2022202420262028
BuiltForecast
Approved 9 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Fondation PHI pour l'art contemporain
- Construction start
- Aug 4, 2025(actual)
- Construction end
- Nov 3, 2028(forecast)
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61041 in the federal list. How to read these figures.