Riverside Drive Water Main Installation

Trout River, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$146,077
Federal share40%

of $365.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
202220232024
Built

Approved 8 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Trout River
Construction start
Jul 31, 2023(actual)
Construction end
Aug 30, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast May 1, 2023
  • Construction end9 months lateforecast Dec 14, 2023

Also in Trout River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61053 in the federal list. How to read these figures.