Forcemain Upgrade

Trout River, Newfoundland and Labrador

completeWastewaterCWWF
Federal contribution
$170,345
Federal share26%

of $655.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Trout River
Construction start
Aug 8, 2017(actual)
Construction end
Oct 10, 2017(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jul 24, 2017
  • Construction end6 months earlyforecast Mar 31, 2018

Also in Trout River

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47041 in the federal list. How to read these figures.