Mental Wellness Unit Development

Whitehorse, Yukon

completeHealthcare InfrastructureCVRIS
Federal contribution
$10.0M
$9,990,000
Federal share100%

of $10.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 4, 2021
2022202320242025
Built

Approved 2 weeks before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Yukon Health Corporation
Construction start
Jun 12, 2023(actual)
Construction end
Aug 15, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2023
  • Construction end3 months lateforecast May 30, 2025