Minnesota Drive Roundabout
Stephenville, Newfoundland and Labrador
Federal contribution
$501,562
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 28, 2022
today
202220232024202520262027
BuiltForecast
Approved 7 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Stephenville
- Construction start
- Apr 1, 2026(forecast)
- Construction end
- Dec 7, 2026(forecast)
Also in Stephenville