Transmission Main from Chlorine Building to West Link Road

Rocky Harbour, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$314,902
Federal share23%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 28, 2022
20222023
Built

Approved 7 months before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Rocky Harbour
Construction start
May 16, 2023(actual)
Construction end
Sep 29, 2023(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 29, 2023

Also in Rocky Harbour

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61165 in the federal list. How to read these figures.