Shears Village Lane and Parsons Lane Paving
Rocky Harbour, Newfoundland and Labrador
Federal contribution
$105,176
Federal share32%
of $331.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Rocky Harbour
- Construction start
- Sep 21, 2023(actual)
- Construction end
- Sep 28, 2023(actual)
Against the original forecast
- Construction start5 months lateforecast May 2, 2023
- Construction end6 months earlyforecast Mar 31, 2024