Water Main CIPP Lining Program
St. John's, Newfoundland and Labrador
Federal contribution
$3.6M
$3,554,570
Federal share40%
of $8.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 13, 2021
20222023
Built
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Oct 15, 2022(actual)
- Construction end
- Nov 4, 2023(actual)
Against the original forecast
- Construction start19 months earlyforecast May 1, 2024
- Construction end13 months earlyforecast Nov 30, 2024
Also in St. John's