Water Main CIPP Lining Program

St. John's, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$3.6M
$3,554,570
Federal share40%

of $8.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 13, 2021
20222023
Built
Program
Green Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Oct 15, 2022(actual)
Construction end
Nov 4, 2023(actual)

Against the original forecast

  • Construction start19 months earlyforecast May 1, 2024
  • Construction end13 months earlyforecast Nov 30, 2024

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61182 in the federal list. How to read these figures.